HoneywellAeroFlow
Supplier Recovery CockpitAerospace · Engines & Power SystemsFabric connected· 6a9f89eeSynthetic dataMHMarcus Hale · Buyer

← Purchase orders

PO-450201 · line 20

Titan Forge Works · P-FORG-2210Compressor disk forging, Ti-6Al-4V

lateconstrained supplierITARHTF7000
Revenue gated
$55.5M
1 end item(s)
PO value
$1.3M
$1,320,000
Quantity open
60
promised 2026-08-28
Past due
11d
confirmed 2026-09-18
Confidence
0.87
dq 0.92

BOM cascade

where the delayed part is used, and what it gates
End itemProgramLevelsQty perGated unitsUnit revenueGated revenue
P-ENG-7000HTF70002230$1,850,000$55,500,000

Derivation

P-ENG-7000: 60 open ÷ 2 per unit = 30 → 30 (floor) × $1,850,000 = $55,500,000 (2 BOM levels)
Line detail
PartP-FORG-2210
Commodityforging
Export classITAR
ProgramHTF7000
Promised2026-08-28
Confirmed2026-09-18
Data quality0.92
Bounded autonomy

A recovery plan for this line can be drafted by the agent fleet, but no communication leaves the system and no system of record is written without a logged human approval.